How Long Does It Really Take to Build a Pool in Murfreesboro? 2026 Timeline + What Actually Causes Delays

Key Points:


  • Most Murfreesboro pool builds take 10 to 12 weeks from groundbreaking to first swim 
  • Rutherford County permit processing adds 2 to 6 weeks depending on season 
  • Middle Tennessee spring weather can delay concrete work by 1 to 2 weeks 
  • Clay-heavy soil in Murfreesboro requires specialized excavation planning 
  • Winter builds often finish faster due to less competition for inspectors 
  • Starting your project in December or January means swimming by April or May 
  • Professional builders with local experience navigate delays more efficiently 


You've decided you want a pool. Amazing! Now comes the question everyone asks: "When can I actually use it?" 


If you're like most homeowners in Murfreesboro, you're probably hoping to be swimming by summer. Maybe you're planning around a specific event, like a graduation party or family reunion. Or perhaps you just want to know if starting now means swimming this season or waiting until next year. 


Here's the truth: pool construction timelines aren't one-size-fits-all. A pool built in Murfreesboro in January will have a different timeline than one started in April. Your specific property, the type of pool you choose, and even which neighborhood you live in can all affect how long your project takes. 


Let's break down exactly what to expect when building a pool in Middle Tennessee, including the real factors that speed things up or slow them down. 


The Short Answer: Average Timeline in Murfreesboro


For a standard inground pool installation in Murfreesboro, you're looking at 10 to 12 weeks from the day we break ground to the day you take your first swim. 


That's the construction timeline. But there's more to the story. 


Before construction even starts, you need to factor in design time (1 to 3 weeks) and permit approval (2 to 6 weeks, depending on the season). So from your first consultation to cannonballing into your new pool, most homeowners should plan on 3 to 5 months total. 


Here's what that looks like in real terms: if you start the process in January, you're swimming by late April or early May. Start in March, and you're looking at late June or July. Begin in May, and you might not be ready until August or September. 


This is why working with an experienced pool builder in Murfreesboro, TN who understands local timelines matters. We can help you plan backward from your target date to figure out when you need to start. 


Phase 1: Design and Planning (1 to 3 Weeks) 


Before any digging happens, you need a solid plan. This phase is where your dream pool takes shape on paper. 


During your initial consultation, we'll visit your property to assess the site, discuss your vision, and take measurements. We'll identify any potential challenges like slopes, utility lines, or drainage issues that could affect construction. 


Then comes the design phase. We'll create detailed plans showing the pool's size, shape, depth, and features. You'll review 3D renderings so you can visualize exactly what your finished pool will look like. This is also when we finalize material selections, lighting, water features, and any additional elements like spas or tanning ledges. 


For straightforward projects where you know exactly what you want, this phase might take just a week or two. If you're still exploring options or making significant customizations, it could stretch to three or four weeks. 


Don't rush this phase. Getting the design right now prevents expensive changes later. 


Once you approve the final design, we move to permitting. 


Phase 2: Permits and Approvals (2 to 6 Weeks) 


This is where things get specifically local, and it's often the most frustrating part of the timeline because you have the least control over it. 


In Rutherford County, pool construction requires permits from the local building department. The county needs to review your plans to ensure they meet setback requirements, safety codes, and zoning regulations. 


During the off-season (November through February), permit processing in Rutherford County typically takes 2 to 3 weeks. The building department isn't as backed up, and reviewers can get to your application more quickly. 


During peak season (March through June), that same permit can take 4 to 6 weeks. Everyone else is also trying to get their pool permitted for summer completion, creating a backlog. 


If you live in a neighborhood with a homeowners association, add another 2 to 4 weeks for HOA architectural review and approval. Some Murfreesboro neighborhoods have specific requirements about pool placement, fencing styles, or even what colors you can use for your pool finish. 


Here's a pro tip: experienced builders submit complete, accurate permit applications the first time. Incomplete applications get kicked back, restarting the clock. At Majestic Swim, we've submitted hundreds of permits in Rutherford County and know exactly what they're looking for. 


Phase 3: Excavation and Site Preparation (2 to 5 Days) 


Once permits are in hand, the real fun begins. Excavation day is exciting because you finally see physical progress. 


In Murfreesboro, excavation typically takes 2 to 3 days for a standard residential pool. However, Middle Tennessee's clay-heavy soil can extend this timeline slightly compared to areas with sandier soil. 


Clay soil is dense and sticky, which means it takes more time and sometimes specialized equipment to excavate properly. On the plus side, clay provides excellent stability for your pool structure. On the downside, it doesn't drain as quickly as sand, so we need to be extra careful about managing water around the excavation site. 


If your property has significant slope or difficult access for equipment, excavation could take 4 to 5 days. We've built pools in some of Murfreesboro's hillier neighborhoods where getting machinery into the backyard required creative problem-solving. 


Rock is the wildcard. Most of Rutherford County doesn't have extensive bedrock near the surface, but it's not unheard of. If we hit rock during excavation, it can add 1 to 3 days for removal. A good site assessment during the design phase usually identifies this risk ahead of time. 


During excavation, we also install the main drain and initial plumbing rough-ins. This groundwork is critical for everything that comes next. 


Phase 4: Steel and Plumbing Installation (1 to 2 Weeks) 


After excavation, we install the steel framework (rebar) that reinforces your pool's structure. This creates the skeleton that the concrete will form around. 


Steel installation for a typical residential pool takes 3 to 5 days. We're building a grid of rebar according to engineering specifications, ensuring your pool will be structurally sound for decades. 


Simultaneously, plumbing work continues. All the pipes that will circulate water, feed your jets and water features, and connect to filtration equipment get installed during this phase. This includes return lines, skimmer lines, and any special plumbing for spas, fountains, or other features. 


Getting plumbing right is crucial because once concrete is poured, making changes is expensive and complicated. This is another reason why the design phase matters so much. 


After steel and plumbing are complete, a Rutherford County inspector needs to come out and approve the work before we can proceed to concrete. Inspector availability can vary, but typically they can schedule within 2 to 3 business days during normal seasons. 


Phase 5: Shotcrete or Gunite Application (1 Day) 


This is one of the most dramatic days of your pool construction. The concrete (either shotcrete or gunite) gets sprayed to form the actual pool shell. 


For most residential pools, the concrete shoot happens in a single day. A specialized crew arrives with their equipment and systematically applies concrete over the steel framework, building up the walls and floor of your pool. 


The process is loud, messy, and absolutely fascinating to watch. Within about 6 to 8 hours, your pool goes from a hole in the ground with exposed rebar to an actual pool-shaped structure. 


Weather plays a big role on concrete day. We can't pour in freezing temperatures, heavy rain, or extreme heat. Middle Tennessee's weather is generally cooperative, but spring can be tricky. March and April bring frequent rain showers that sometimes force us to reschedule concrete pours. 


If your scheduled concrete day gets rained out, we typically reschedule within 3 to 5 days, weather permitting. This is one reason why winter builds in Tennessee often proceed more smoothly than spring builds, even though it seems counterintuitive. 


Phase 6: Concrete Curing (7 to 10 Days)


After the concrete shell is formed, it needs time to cure and gain strength. You can't rush this phase. 


Proper curing takes at least 7 days, though we typically allow 10 days before moving to the next phase. The concrete needs to reach sufficient strength to handle the stress of tile work and finishing. 


During curing, we keep the concrete moist to prevent cracking. This is especially important during Tennessee's hot summer months when rapid drying can cause problems. 


There's not much visible activity during this phase, which can feel frustrating when you're eager to see progress. But this waiting period is essential for a pool that will last 50+ years. 


We use this time to prepare for the next phases, scheduling tile crews and coordinating equipment delivery. 


Phase 7: Tile and Coping Installation (3 to 5 Days) 


Once the concrete has cured sufficiently, we install the tile (the decorative band around the waterline) and coping (the cap around the pool's edge). 


For a standard pool, tile and coping installation takes 3 to 5 days. Custom designs with intricate patterns or specialty materials can take a bit longer. 


This is where your pool starts to look finished. The coping provides a clean edge and defines the pool's shape, while the waterline tile adds visual interest and helps mark the water level. 


Material choices affect timing here. Natural stone coping sometimes requires more time to install than precast concrete coping because each piece needs individual fitting. Glass tile mosaics take longer than standard ceramic tile. 


Weather matters less during this phase since most of the work is relatively protected, but we still can't work in heavy rain or freezing conditions. 


Phase 8: Interior Finish Application (1 to 3 Days)


The interior finish is what you'll see and feel when you're in the pool. Options include plaster, pebble finishes, or aggregate finishes. 


Standard plaster application takes 1 to 2 days. More complex finishes like pebble or quartz aggregates might take 2 to 3 days because they require additional steps. 


This is another weather-dependent phase. We need dry conditions and moderate temperatures for the finish to cure properly. Middle Tennessee's humidity actually helps with curing compared to drier climates, but we still need to avoid rain. 


The finish crew needs to work quickly and precisely because once they start, they need to complete the entire pool in one continuous session. You can't partially finish a pool and come back later. 


After the finish is applied, there's another brief curing period (usually 24 to 48 hours) before we can start filling the pool. 


Phase 9: Decking and Hardscaping (1 to 2 Weeks) 


While the interior finish cures, we shift focus to the area around your pool. This includes pouring concrete decking, installing pavers, or creating other hardscape features. 


A basic concrete deck takes 3 to 5 days to pour and finish. Stamped or decorative concrete might take 5 to 7 days. Paver installation generally requires 1 to 2 weeks depending on the size and complexity of the pattern. 


This phase often overlaps with other work. While the deck crew works on one area, the equipment installation crew might be working on another part of the project. 


For comprehensive outdoor living design projects that include outdoor kitchens, fire features, or extensive landscaping, this phase can extend to 3 or 4 weeks. That's why it's important to clarify upfront exactly what's included in your pool project versus what might be additional work. 


Phase 10: Equipment Installation (2 to 3 Days)  


Your pool's mechanical systems (pump, filter, heater, automation controls) get installed and connected during this phase. 


Equipment installation typically takes 2 to 3 days. This includes: 


  • Setting and connecting the pump and filter 
  • Installing the heater if you're adding one 
  • Wiring electrical connections 
  • Setting up automation systems 
  • Installing lighting controls 
  • Connecting salt systems or other water treatment equipment 


Electrical work requires another inspection from Rutherford County. As with previous inspections, scheduling usually takes 2 to 3 business days. 


At Majestic Swim, we often use this time to train you on your new equipment. Understanding how to operate your system prevents problems down the road and helps you get the most from your investment. 


Phase 11: Filling and Startup (2 to 3 Days)


The moment you've been waiting for: filling your pool! 


Filling a typical residential pool takes 12 to 24 hours depending on your water pressure. In Murfreesboro, most homes on city water can fill a pool overnight or over the course of a day. 


If you're on well water, filling takes longer and you'll need to monitor your well's recovery rate to avoid running it dry. Some homeowners opt to have water delivered by truck to speed up the process. 


Once the pool is full, we start up all the equipment and begin balancing the water chemistry. This takes another 24 to 48 hours. We need to get pH, alkalinity, calcium hardness, and sanitizer levels all in the proper range before the pool is safe for swimming. 


New plaster finishes require a special startup procedure that includes brushing the pool daily for the first week and carefully managing chemistry to prevent staining or etching. We'll walk you through this process and often handle the first few days ourselves to ensure everything starts off right. 


Phase 12: Final Inspection and Walkthrough (1 Day) 


Before you can officially use your pool, we need a final inspection from Rutherford County to confirm everything meets code. 


We'll also do a comprehensive walkthrough with you, covering: 


  • How to operate all equipment 
  • Basic maintenance procedures 
  • Water chemistry basics 
  • Safety features and rules 
  • Warranty information 
  • Seasonal care instructions 


This walkthrough typically takes 1 to 2 hours. We want you to feel completely confident about maintaining and enjoying your new pool. 


And then... you're swimming!




What Actually Causes Delays in Murfreesboro Pool Construction?


Even with the best planning, delays happen. Here are the most common culprits in Middle Tennessee:


Weather Delays


Middle Tennessee weather is unpredictable, especially in spring. March through May brings frequent rain systems that can interrupt multiple phases of construction. 


Heavy rain delays excavation, concrete pours, and finish work. We can't work in standing water or when the ground is saturated. A rainy week can easily add 5 to 7 days to your timeline. 


This is one reason why starting your pool project in winter actually works well in Tennessee. Our winters are relatively mild with less rainfall than spring. December through February builds often encounter fewer weather delays than April through June builds. 


Permit Processing Delays 


During peak season (March through June), Rutherford County's building department gets slammed with permit applications. Everyone wants to build their pool for summer use. 


If there's any issue with your application (missing information, unclear details, questions about setbacks), the process stops until it's resolved. This is why working with experienced local builders matters. We know exactly what Rutherford County requires and submit complete applications. 


HOA approvals add another layer. Some Murfreesboro neighborhood associations only meet monthly, which means if you just miss their meeting, you're waiting another month for approval. 


Equipment or Material Shortages 


During peak season (March through June), Rutherford County's building department gets slammed with permit applications. Everyone wants to build their pool for summer use. 


If there's any issue with your application (missing information, unclear details, questions about setbacks), the process stops until it's resolved. This is why working with experienced local builders matters. We know exactly what Rutherford County requires and submit complete applications. 


HOA approvals add another layer. Some Murfreesboro neighborhood associations only meet monthly, which means if you just miss their meeting, you're waiting another month for approval. 


Equipment or Material Shortages 


While this is less common than it was during the pandemic years, specialty equipment or materials can occasionally be on backorder. 


Custom tile, specific lighting systems, or high-end automation equipment sometimes have longer lead times. If your heart is set on a particular product that's backordered, it could delay your project by several weeks. 


This is another reason to start the design process early. If we know in January that you want a specific tile that has a 12-week lead time, we can order it immediately and it arrives exactly when we need it during construction. 


Inspection Scheduling Conflicts


Rutherford County inspectors have a lot of ground to cover. During peak construction season, getting an inspector to your site within a day or two can be challenging. 


Each phase of pool construction requires inspection before moving forward (steel inspection, electrical inspection, final inspection). If an inspector can't come out for a week, your project sits idle waiting. 


This rarely adds more than a few days to the timeline, but it's something to be aware of. 


Utility Line Conflicts


Sometimes during excavation we discover utility lines that weren't properly marked or documented. Gas lines, electric lines, water lines, or old irrigation systems can all require careful navigation. 


If we need to reroute or relocate a utility, it can add several days to the excavation phase. This is why proper site assessment and utility location services before construction are so important. 


Underground Obstacles 


Rock, old building foundations, buried debris, or unexpected groundwater can all slow down excavation. 


In most of Murfreesboro, these issues are rare. But occasionally we encounter surprises. A concrete patio from 30 years ago that was buried rather than removed. An old septic system that wasn't properly documented. A spring that wasn't apparent during dry weather. 


Professional excavation crews know how to handle these situations, but they do add time to the project. 


Best Time to Start Your Pool Project in Murfreesboro 


f you want to minimize delays and maximize your first swimming season, here's the smart play: start your project in December, January, or February. 


Yes, it feels weird to start a pool project in winter. But here's why it works: 


Faster permit processing. The building department isn't backlogged with spring applications. You'll get your permits in 2 to 3 weeks instead of 5 to 6 weeks. 


Better contractor availability. Most pool builders have lighter schedules in winter, which means your project gets more focused attention and can proceed more quickly. 


Fewer weather delays. Middle Tennessee winters are relatively dry compared to spring. You'll encounter fewer rain delays during critical phases like excavation and concrete work. 


Ready for peak season. A project started in December or January is typically finished by April or May, giving you the entire summer to enjoy your pool. 


The only real weather risk in winter is occasional freezing temperatures. If we hit a week of sustained freezing weather, concrete work pauses. But this is relatively rare in Murfreesboro and usually only delays the project by a few days. 


Starting in March, April, or May means competing with everyone else who wants their pool done for summer. You'll face longer permit times, busier contractors, and more weather delays. A project started in April might not be ready until July or August. 


If you're reading this and thinking "I wish I'd known this six months ago," don't worry. We can still build you an amazing pool. The timeline just might extend into late summer or early fall. 


How Majestic Swim Keeps Projects on Schedule 


We've built hundreds of pools in Middle Tennessee, and we've learned how to minimize delays and keep projects moving efficiently. 


Here's what we do differently: 


Thorough site assessment upfront. We identify potential issues during the design phase, not during excavation when they're expensive to fix. We call for utility locates, assess soil conditions, and plan for drainage before we ever submit permit applications. 


Complete permit applications. We know exactly what Rutherford County requires and submit applications that get approved the first time. No back-and-forth, no resubmissions, no wasted weeks. 


Strategic scheduling. We plan the sequence of work to minimize weather-dependent tasks during Tennessee's rainy seasons. We coordinate inspections proactively rather than waiting until we're ready and then hoping for quick availability. 


Established relationships with inspectors. When you build in Rutherford County regularly, you develop working relationships with the inspection staff. They know our work meets code, which often results in faster scheduling and smoother inspections. 


In-house crews for critical phases. We don't subcontract every aspect of the build. Our own crews handle key phases, which means we control the schedule rather than waiting on someone else's availability. 


Realistic timelines from the start. We'd rather under-promise and over-deliver than tell you 8 weeks and actually take 14. Our estimates account for realistic permit times, normal weather patterns, and inspection scheduling. 


Proactive communication. If weather delays a concrete pour or an inspector reschedules, you'll know immediately. We keep you updated throughout the process so you're never wondering what's happening with your project. 


Your Custom Timeline


Every property is different. Your specific timeline depends on: 


  • The size and complexity of your pool design 
  • Whether you're adding a spa, water features, or extensive hardscaping 
  • Your property's accessibility and site conditions 
  • The time of year you start construction 
  • HOA requirements in your neighborhood 
  • Current permit processing times in Rutherford County 


The best way to get an accurate timeline for your specific project is to schedule a consultation. 


We'll visit your property, assess your site, discuss your vision, and give you a realistic timeline based on when you want to start and what you want to build. No guessing, no generic estimates. Just honest information based on years of building pools throughout Middle Tennessee. 


Ready to Start Planning Your Timeline? 


Now you know exactly what to expect when building a pool in Murfreesboro. From initial design through that first cannonball, you understand each phase and what can affect the schedule. 


The biggest factor you control is when you start. Beginning your project in winter means swimming by late spring. Starting in spring means waiting until mid or late summer. The choice is yours. 


At Majestic Swim, we're currently scheduling consultations for projects throughout 2026. If you want to be swimming this summer, now is the time to start the conversation. 


Check out our project galleries to see completed pools and get inspired for your own backyard transformation. 


Ready to get your custom timeline? Contact us at (615) 691-2500 or email Info@MajesticSwim.com to schedule your free consultation. We'll visit your property, discuss your vision, and give you an exact timeline for your specific project. Visit us at 1522 Glenridge Dr, Murfreesboro, TN 37128, or explore our work at www.majesticswim.com. Let's figure out when you can start swimming in your dream pool! 

FAQs About Pool Construction Timelines in Murfreesboro 

How long does it take to build a pool in Murfreesboro, TN?


The average pool construction timeline in Murfreesboro is 10 to 12 weeks from groundbreaking to first swim. However, you need to add 2 to 6 weeks for permits and 1 to 3 weeks for design. Total time from first consultation to swimming is typically 3 to 5 months, depending on the season and project complexity.


What time of year is best to build a pool in Tennessee?


December through February is actually the best time to start a pool project in Tennessee. Winter builds face fewer permit delays, less competition for contractors and inspectors, and generally drier weather than spring. A project started in January is typically ready by April or May, giving you the full summer to enjoy your pool.


How long does it take to get a pool permit in Rutherford County? 


Rutherford County pool permits take 2 to 3 weeks during off-season (November through February) and 4 to 6 weeks during peak season (March through June). If you live in an HOA neighborhood, add another 2 to 4 weeks for architectural review and approval.


Can you build a pool in winter in Tennessee?


Yes! Tennessee's mild winters make year-round pool construction possible. The main limitation is sustained freezing temperatures, which prevent concrete work. However, freezing weather is relatively rare in Murfreesboro and usually only causes brief delays. Winter builds often proceed faster due to fewer weather and permitting delays.


What causes delays in pool construction?


The most common delays in Murfreesboro pool construction are weather (especially spring rain), peak-season permit backlogs, inspection scheduling during busy periods, and occasional equipment or material delivery issues. Experienced local builders minimize these delays through strategic scheduling and thorough planning.


How long does pool excavation take?


Pool excavation in Murfreesboro typically takes 2 to 3 days for a standard residential pool. Middle Tennessee's clay-heavy soil can extend this slightly compared to sandier regions. Properties with significant slope, difficult access, or unexpected rock can take 4 to 5 days.


Do I need to be home during pool construction? 


You don't need to be home for most of the construction process, but you should be available for the initial consultation, design review, and final walkthrough. Many homeowners enjoy watching key milestones like excavation and concrete pour, but it's not required.


Can weather delay my pool construction? 


Yes, weather is the most common cause of construction delays in Middle Tennessee. Heavy rain delays excavation, concrete pours, and finish work. Spring (March through May) typically brings more rain-related delays than winter months. A rainy week can add 5 to 7 days to your overall timeline.

FAQs About Majestic Swim


How does Majestic Swim minimize construction delays? 


We minimize delays through thorough site assessments, complete permit applications that get approved the first time, strategic scheduling that accounts for weather patterns, established relationships with Rutherford County inspectors, and proactive communication. We've built hundreds of pools in Middle Tennessee and know exactly how to navigate local challenges. 


Does Majestic Swim provide a guaranteed timeline? 


We provide realistic timelines based on your specific project, season, and site conditions. While we can't control weather or inspector availability, we can give you accurate expectations based on our extensive experience in Murfreesboro. We'd rather under-promise and over-deliver than set unrealistic expectations.


What areas does Majestic Swim serve? 


Majestic Swim is based in Murfreesboro and serves homeowners throughout Middle Tennessee, including Nashville, Murfreesboro, and surrounding communities. Our deep knowledge of Rutherford County permitting and local conditions helps us complete projects efficiently.


Can I see examples of completed Majestic Swim projects? 


Absolutely! Visit our testimonials page to hear from happy customers, and browse our project galleries to see completed pools throughout Middle Tennessee. You'll get a sense of our work quality and the variety of pools we've built.


How do I get a custom timeline for my pool project? 


Call us at (615) 691-2500 or email Info@MajesticSwim.com to schedule a free consultation. We'll visit your property, assess your site, discuss your vision and timeline goals, and provide a detailed schedule specific to your project. Visit our showroom at 1522 Glenridge Dr, Murfreesboro, TN 37128, or explore our services at www.majesticswim.com!

Disclaimer: The information provided on this blog is for general informational purposes only and should not be considered professional advice. While we strive to ensure that all content is accurate and up to date, no guarantees are made regarding its completeness or reliability. Readers are encouraged to seek professional guidance specific to their situation before making any decisions based on the information provided. The author and this blog disclaim any liability for actions taken or not taken based on the content herein.

Grid of 12 different swimming pool layout designs with surrounding greenery and paths.
March 17, 2026
Not sure what size pool fits your yard? Learn how to choose the perfect pool dimensions for your space, budget, and lifestyle in Tennessee. Get expert sizing tips from Majestic Swim.
February 13, 2026
Discover the hottest pool design trends for 2026, from natural lagoon styles to smart technology. Get inspired by the latest materials, lighting, and features for your Tennessee backyard pool.
February 11, 2026
Thinking about building a pool in Tennessee? Learn what goes into planning a successful pool project, from design and permits to timelines and outdoor living features, with help from Majestic Swim.
February 11, 2026
Discover why winter pool installation in Tennessee offers better pricing, faster timelines, and spring readiness. Learn the benefits of building your dream pool during the off-season.
A pink donut pool float in a turquoise pool with silver water fountains.
October 8, 2025
Transform your backyard pool with stunning water features. Expert design tips for fountains, waterfalls, and more from Murfreesboro's premier pool builders at Majestic Swim.
Swimming pool with a safety fence, sun loungers, and a sunshade on a patio.
August 15, 2025
Discover essential pool safety features for Tennessee families. From required barriers to smart technology, learn how to keep your family safe around pools.
Woman in a blue swimsuit and straw hat applying sunscreen by a pool on a sunny day.
August 5, 2025
Think it's too late for pool installation? Discover why August is actually ideal timing for your Tennessee pool project. Expert insights from Murfreesboro builders.
waterfall fountain in a pool
August 4, 2025
Transform your Tennessee pool with stunning water features. Explore waterfalls, fountains, and custom features that create resort-style backyards in Middle Tennessee.
Outdoor swimming pool with clear blue water, surrounded by trees and open sky in the background.
July 3, 2025
Think your Murfreesboro backyard is too small for a pool? Discover compact pool solutions that maximize space and create stunning results in smaller yards.
Swimming Pool
May 20, 2025
Thinking about switching to a saltwater system? Learn why fiberglass pools are ideal for saltwater, how to maintain your system, and the pros and cons. Brought to you by Majestic Swim. Serving homeowners in Murfreesboro, TN and surrounding areas.